Special survey Dec 31, 2021 · planned Nov 1, 2021 → Nov 19, 2021
Class items closed. Steel renewal ran over the estimate; the deferred item is booked for the intermediate survey.
Each PMS item is the job itself: open it on its job card. Yard items are extra work.
| Yard item | Hull blasting | 10,620 m² | Done | |
| Yard item | Hull painting | 10,360 m² | Done | |
| Yard item | Anode renewal | 120 pcs | Done |
| Yard item | Propeller polish | 1 ea | Deferred |
| Yard item | Tank cleaning | 6 tanks | Done |
Three yards priced per item, plus the dock fee for their days in dock. Green is the lowest price per line.
| Item | Kestrel Bay Shiprepair Awarded | Marrowgate Drydocks | Solvenna Marine Yard |
|---|---|---|---|
| PM-2082Emergency generator load test | $12,130 | $14,220 | $12,290 |
| PM-2123Lifeboat launching drill and davit check | $13,300 | $16,490 | $11,660 |
| PM-2169Steering gear test and inspection | $11,560 | $11,660 | $17,000 |
| PM-2201Unit overhaul: piston, liner and rings | $13,990 | $16,810 | $12,900 |
| PM-2229Turbocharger bearing renewal | $12,120 | $14,350 | $16,140 |
| Hull blasting | $71,490 | $58,310 | $62,420 |
| Hull painting | $112,620 | $107,750 | $105,370 |
| Anode renewal | $25,570 | $29,230 | $27,640 |
| Propeller polish | $4,500 | $4,430 | $5,840 |
| Tank cleaning | $39,250 | $37,490 | $50,920 |
| Dock fee | $156,800 · 16 days | $224,000 · 20 days | $186,900 · 21 days |
| Total | $473,330 | $534,740 | $509,080 |
Growth work found in the yard. Each one is approved by a person with publish access.