Special survey Dec 31, 2024 · planned Nov 1, 2024 → Nov 19, 2024
Special survey passed. Hull coated to the full spec; one item deferred to the next docking with class agreement.
Each PMS item is the job itself: open it on its job card. Yard items are extra work.
| Yard item | Hull blasting | 12,500 m² | Done | |
| Yard item | Hull painting | 11,740 m² | Done | |
| Yard item | Anode renewal | 120 pcs | Deferred |
| Yard item | Propeller polish | 1 ea | Done |
| Yard item | Tank cleaning | 6 tanks | Done |
Three yards priced per item, plus the dock fee for their days in dock. Green is the lowest price per line.
| Item | Kestrel Bay Shiprepair | Marrowgate Drydocks Awarded | Solvenna Marine Yard Lowest |
|---|---|---|---|
| PM-2012Steering gear test and inspection | $14,700 | $12,990 | $12,150 |
| PM-2117Emergency generator load test | $14,800 | $15,570 | $14,550 |
| PM-2142Lifeboat launching drill and davit check | $12,490 | $15,390 | $15,820 |
| PM-2205Unit overhaul: piston, liner and rings | $16,680 | $12,270 | $15,070 |
| PM-2221Turbocharger bearing renewal | $14,240 | $15,110 | $14,200 |
| Hull blasting | $72,400 | $71,300 | $89,080 |
| Hull painting | $90,400 | $120,570 | $94,890 |
| Anode renewal | $29,650 | $30,650 | $29,530 |
| Propeller polish | $3,980 | $4,880 | $5,490 |
| Tank cleaning | $48,310 | $48,500 | $46,390 |
| Dock fee | $196,000 · 20 days | $179,200 · 16 days | $133,500 · 15 days |
| Total | $513,650 | $526,430 | $470,670 |
Growth work found in the yard. Each one is approved by a person with publish access.