Special survey Dec 31, 2026 · planned Nov 1, 2026 → Nov 19, 2026
Each PMS item is the job itself: open it on its job card. Yard items are extra work.
| Yard item | Hull blasting | 9,720 m² | Open | |
| Yard item | Hull painting | 9,900 m² | Open | |
| Yard item | Anode renewal | 120 pcs | Open |
| Yard item | Propeller polish | 1 ea | Open |
| Yard item | Tank cleaning | 6 tanks | Open |
Three yards priced per item, plus the dock fee for their days in dock. Green is the lowest price per line.
| Item | Kestrel Bay Shiprepair | Marrowgate Drydocks Lowest | Solvenna Marine Yard |
|---|---|---|---|
| PM-2082Emergency generator load test | $13,980 | $12,170 | $15,930 |
| PM-2123Lifeboat launching drill and davit check | $12,080 | $13,750 | $14,190 |
| PM-2169Steering gear test and inspection | $15,630 | $15,140 | $12,020 |
| PM-2201Unit overhaul: piston, liner and rings | $13,530 | $12,830 | $13,390 |
| PM-2229Turbocharger bearing renewal | $14,780 | $14,620 | $13,850 |
| Hull blasting | $60,890 | $55,840 | $58,350 |
| Hull painting | $86,470 | $92,330 | $107,670 |
| Anode renewal | $30,050 | $27,150 | $28,160 |
| Propeller polish | $5,380 | $5,540 | $4,500 |
| Tank cleaning | $46,490 | $45,040 | $38,080 |
| Dock fee | $205,800 · 21 days | $190,400 · 17 days | $186,900 · 21 days |
| Total | $505,080 | $484,810 | $493,040 |
Growth work found in the yard. Each one is approved by a person with publish access.